|
Variance
Request |
Variance Request Submitted |
Variance
Issued |
Location |
Description |
| 1 |
May 22, 2012 |
June 4, 2012 |
Substation/Switchyard |
Shift of the 30-acre substation/switchyard approximately 565 feet to the north in order to minimize disturbance to areas that have the potential of cultural importance. |
| 2 |
May 31, 2012 |
June 12, 2012 |
12 turbine locations including 135, 162, 163, 164, 165, 161, 167,
168, 172, 125, 128 and 126
|
Conduct geotechnical investigations at 12 turbines sites that are within
500 feet of the Palm Springs formation.
|
| 3 |
June 4, 2012 |
June 12, 2012 |
Western Colorado Desert Routes of Travel (WECO) Routes in study area |
Temporary use of the BLM’s WECO routes in order to complete pre-construction surveys as identified in the Final EIR/EIS and Record of Decision (ROD). |
| 4 |
June 4, 2012 |
June 20, 2012 |
WECO Routes in study area |
Temporary use of BLM WECO routes outside those designated as approved project roads in the ROD for geotechnical rigs to access turbine locations to conduct the required further geotechnical investigations. |
| 5 |
July 2, 2012 |
July 12, 2012 | 43 turbine locations and 31 access roads |
Micro-siting wind turbine locations and associated road re-alignments to minimize potential disturbance to environmentally sensitive resources. |
| 6 |
July 3, 2012 |
July 24, 2012 |
Substation/Switchyard |
Work space modification at the substation/switchyard and transmission line turning structures. |
| 7 |
June 26, 2012 |
August 1, 2012 |
Wind turbines 9, 104, 107, 126, 135 and 167. |
Modify alternate turbine locations included in the Record of Decision. |
| 8 |
July 20, 2012 |
July 27, 2012 |
Access road to wind turbine 9. |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 9 |
July 20, 2012 |
July 30, 2012 |
Underground collection line corridor between County Route S2 and Dos Cabezas Road. |
Re-alignment of underground collection line corridor. |
| 10 |
August 8, 2012 |
August 10, 2012 |
Access road between wind turbine 101 and 102. |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 11 |
July 27, 2012 |
August 16, 2012 |
Wind turbine 176. |
Micro-siting turbine location to accommodate a third party interest group.
|
| 12 |
August 14, 2012 |
August 17, 2012 |
Work space for Wind turbine 103, 134 and 135. |
Work space modification at wind turbine pad sites. |
| 13 |
August 16, 2012 |
August 17, 2012 |
Collection line routing for wind turbines 155, 156 and 159. |
Underground collection line corridor refinement. |
| 14 |
August 21, 2012 |
August 30, 2012 |
Wind turbines 86 and 87 |
Micro-siting turbine locations and a road re-alignment to minimize potential disturbance to environmentally sensitive resources. |
| 15 |
August 22, 2012 |
September 4, 2012 |
Wind turbines 26, 27 and 28. |
Micro-siting turbine locations to accommodate a third party interest
group.
|
| 16 |
August 20, 2012 |
August 23, 2012 |
Work areas adjacent to wind turbine pad sites. |
Work space requirements associated with support safety tag lines. |
| 17 |
August 22, 2012 |
August 30, 2012 |
Wind turbine 69. |
Work space modification at wind turbine pad site. |
| 18 |
August 28, 2012 |
September 5, 2012 |
Underground collection line corridors near wind turbines 88 and 131. |
Re-alignment of underground collection line corridors. |
| 19 |
August 31, 2012 |
September 17, 2012 |
Access road to wind turbine 73. |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 20 |
August 31, 2012 |
September 13, 2012 |
Access road to wind turbine 30 and access road to wind turbine 78. |
Re-alignment of two access roads to minimize potential disturbance to environmentally sensitive resources. |
| 21 |
September 13, 2012 |
September 28, 2012 |
Access road to wind turbine 11 and access road between wind turbines 81 and 87. |
Re-alignment of two access roads to minimize potential disturbance to environmentally sensitive resources. |
| 22 |
September 19, 2012 |
October 2, 2012 |
Underground collection line corridor from wind turbine 90 to 93. Turning radii near wind turbines 92 and 95. |
Re-alignment of underground collection line corridors and extension of two turning radii. |
| 23 |
September 21, 2012 |
October 15, 2012 |
Underground collection line corridor along County Highway S2 and access road near wind turbine 64. |
Re-alignment of underground collection line corridor and modification to access road. |
| 24 |
September 27, 2012 |
October 9, 2012 |
Wind turbines 19 and 20. |
Re-alignment of an access road and micro-siting a turbine location to minimize potential disturbance to environmentally sensitive resources. |
| 25 |
October 4, 2012 |
October 10, 2012 |
Wind turbines 16 and 17 |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 26 |
October 11, 2012 |
November 14, 2012 |
Wind turbines 9 and 10 |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 27 |
October 12, 2012 |
October 22, 2012 |
Wind turbine 98 |
Micro-siting a turbine location to accommodate a third party interest group.
|
| 28 |
October 16, 2012 |
October 19, 2012 |
Wind turbine 168 |
Micro-siting a turbine location to minimize potential disturbance to environmentally sensitive resources. |
| 29 |
October 16, 2012 |
October 26, 2012 |
Wind turbines 49, 50, and 51 |
Re-alignment of an access road and shifting a turbine location to minimize potential disturbance to environmentally sensitive resources. |
| 30 |
October 17, 2012 |
October 25, 2012 |
Wind turbine 164 |
Re-alignment of an access road and micro-siting a turbine location to minimize potential disturbance to environmentally sensitive resources. |
| 31 |
October 17, 2012 |
October 25, 2012 |
Wind turbine 161 |
Micro-siting a turbine location to minimize potential disturbance to environmentally sensitive resources. |
| 32 |
October 19, 2012 |
October 25, 2012 |
Wind turbines 165 and 167 |
Re-alignment of an access road and underground collection line corridor. |
| 33 |
October 20, 2012 |
October 24, 2012 |
Dos Cabezas Road between wind turbine 16 and 18 |
Re-alignment of an access road to minimize potential disturbance to environmentally sensitive resources. |
| 34 |
November 1, 2012 |
December 6, 2012 |
Wind turbines 116, 118, 120, 122, 123, 124, 125, 126, and 128 and access road to the Site 2 turbines. |
Shifting turbine locations to accommodate a third party interest
group, modifying the disturbance limits at several turbine locations, re-alignment of an access road to minimize potential disturbances, and removal of an approved equipment laydown area.
|
| 35 |
November 21, 2012 |
December 7, 2012 |
Wind turbines 49 and 126. |
Work space modifications at wind turbine pad sites. |
| 36 |
November 27, 2012 |
December 19, 2012 |
Wind turbine 167. |
Micro-siting a turbine location to mitigate geotechnical siting considerations. |
| 37 |
February 20, 2013 |
March 5, 2013 |
Asphalt paved road between Highway S2 and the 30-acre Substation/Switchyard |
Work space modification at two planned low water crossings. |
| 38 |
February 22, 2013 |
March 5, 20131 |
Wind turbines 120, 126, and 167 |
Micro-siting turbine locations to mitigate geotechnical siting considerations. |
| 39 |
March 29, 2013 |
April 12, 2013 |
Area between wind turbines 161 and 168 |
Placement of soil to minimize the potential for ponding. |
This page contains tables and is
best viewed with Netscape or Internet Explorer. Please report any problems to
the web
coordinator.
1 Engineering drawings that are proprietary to OE LLC have been redacted from the variance approval.
Related Links:
OWEF Project
(BLM website) BLM NEPA compliance and decision documents available here.
Imperial County Planning & Development
(Imperial County Final EIR/EIS website)
OWEF Project
(Pattern Energy Website)
|
|